PRACTICAL SAFETY CASE
DEVELOPMENT
In a number of offshore
environments a safety case is required, either by the flag
state or by the operator, so rig owners will hire some
suitably experienced and expert organisation to produce the
required document, and the result will be submitted for
admiration and in some cases, approval. In many cases the
whole activity will pass the workforce by, who will only be
aware of the existence of the document if they have access
to the OIM’s office. Of course the rig manager will have one
as well, visible on his shelf of important documents. He
will regard it as his licence to drill.
The compilation is invariably extremely expensive so it
should be more than a heavy weight which can be used to keep
doors open. A big stone would do the same thing. Surely we
can do better?
As a result of the enquiry into the loss of the UK
production platform Piper Alpha, offshore installations
working in the British sector of the North Sea were required
to be provided with safety cases. Lord Cullen who headed the
enquiry suggested that they would encapsulate, in one
document, the information which would be required to prove
that an installation was operating as safely as possible in
the offshore environment. This recommendation was only one
of more than 130. Another was that offshore safety was to be
administered by the UK Health and Safety Executive, who even
then were becoming notorious for, among other things,
apparently requiring school children to wear safety glasses
when playing conkers.
There were few consultants developing mobile unit safety
cases at the time, and much of the expertise both in the HSE
and the drilling industry was recruited from the nuclear
consultancies most of whom were based in Warrington. While
they were expert at developing and assessing QRA
(Quantitative Risk Assessment) few had much knowledge of the
marine world. Another failing in the earliest safety cases
was a realistic means of assessing hazards, and as a result
a number of qualitative assessment techniques were
developed, one of which was the “bow-tie”, which was
pioneered in UK by EQE (Earthquake Engineering).
Over the years a variety of safety case templates have been
developed with the intention of assisting rig owners with
the task, which remains onerous. As a result the templates
have become extremely complex, tending to ensure that the
document will continue to be compiled by consultancies, and
that they will remain opaque, and of little use to anyone
except the producers of the document and in the end, the
assessors who determine whether it is actually a case for
safety. The latest templates contain more words, more
matrices, more evaluation processes and more acronyms, but
seem to have mislaid the original objective.
Of course the templates are approved by committees, and it
is natural that they should not wish to commit the industry
to anything too onerous, so these documents are gradually
reduced to processes with limited value. Will today’s IADC
template actually contribute to the safety of those
offshore? What-ever its intentions does it just look like a
paper exercise? There are pertinent questions like “How can
you carry out a risk assessment without having any
recommendations?” and “How can you have a risk matrix for
major accidents which included a level of “several times a
year at the location” when the most frequent major accident
should not occur more than once in 1000 years on any
installation?
In the UK there has been a second iteration of the safety
case regulations which have resulted, among other things, in
a closer relationship between the regulations themselves and
the supporting legal requirements, PFEER (The Prevention of
Fire and Explosion and Emergency Response) regulations, DCR
(The Design and Construction Regulations) and MAR (The
Management and Administration Regulations). The new
regulations also specifically require consultation with the
workforce, and that at suitable intervals the case should be
reviewed by some-one who had not been involved in the
production of the original case.
But so much for the history and the possible failings in
what has been put in place so far. What is to be done? We
probably need to go back to what Lord Cullen intended in
order to find a way forward, and to make the safety case a
valuable document, not just for the rig manager who gets his
licence to drill, or the HSE or other regulatory body who
get to feel that they are doing the right thing, or for the
consultancies who make money out of the whole business. He
intended that the compilation of the document would assist
in the maintenance of a suitable safety management system,
and that the system would be visible to the workforce, and
that the details of the installation should be included,
because they would be unlikely to exist anywhere else, and
that the risks in the operation of the unit should be
assessed in order to ensure that they would be reduced to an
acceptable level. And importantly as part of the process of
assessment, improvements in the existing systems, structure
and procedures would be identified and put in place.
We have more or less accepted that the case should be
divided into six sections, since all templates have followed
this layout for some years, but what is important is the
content. Everyone accepts that section one should contain
the road map for the rest of the document, so we can put it
to one side. Section Two has traditionally contained the
summary of the safety management system and there are a
number of guidance documents which can be used to ensure
that this contains the appropriate information. So at this
point the safety case compilation will assist the owners of
the unit to ensure that their safety management system
contains what is required to keep people safe. Identified
deficiencies, if any, can be addressed during the
development of the case. However, it may be best to
summarise the various components of the system, rather than
writing a few words followed by a reference. References were
recommended by the original guidance to the 1993 safety case
regulations but it may be time to limit their use.
References obviously required the reader to look at other
documents, or in some cases at other sections of the safety
case, with the result that the section itself is often
almost impossible to read.
Section three has become the repository for the “technical
details” of the installation. It would seem to be the
simplest thing in the world just to write out the
specification of the equipment on the rig. Surely everybody
knows, or some people know what there is in the way of
equipment. Sadly this is not so, and often compilers
researching the details of an installation will find
conflicting information written in different places. Often
such problems are resolved by writing stuff that is so vague
that it is no good to anyone. At the very least the
compilers should carry out in depth research on one rig of a
class, possibly including the extreme measure of reading the
specification of the equipment off the attached brass
plates, and tracing the ventilation ducts from individual
compartments to the vents on the exterior of the unit. Those
who consider such detail as excessive should have a look at
the transcripts of the witness statements from the Deepwater
Horizon investigation. Members of the rig crew have had
differing views as to how some essential equipment operated.
Once a single rig of a class has been thoroughly researched,
the details can be checked by the engineering department of
other rigs. This ensures that the details are correct, and
therefore have a value for the existing and future crew
members.
Section four is the dreaded risk assessment section. There
is more than one way of dealing with this, and as a basis
what-ever processes are used it could be best to develop a
separate risk assessment document and to summarise it in the
safety case. The case should therefore contain a description
of the processes used, and what the results are, and as far
as possible both the description and the results should be
presented in a way that the workforce can understand. Lord
Cullen was very keen on the inclusion of QRA (Quantitative
Risk Assessment) in the risk assessment, and the HSE in UK
set a standards that the IRPA (Individual Risk Per Annum)
for each offshore worker should be less than 1 x 10-3.
Attempts at an explanation will only increase the level of
boredom, and this is the problem with QRA. It has a use, but
no-one except for statisticians understand it, and it is
easy to manipulate. We are better off concentrating on
qualitative risk assessments, all of which can involve the
workforce. One of the most effective is the bow-tie method
which if properly used, is conducted by a facilitator
assisting members of the rig’s team to assess the barriers
in place which would prevent major accidents and the
mitigation measures which would reduce their consequences.
The technique allows failings to be identified and therefore
for recommendations to be made.
Mitigation is the means by which the effects of major
accidents are limited. In the event that the accident
happens, it is essential that the management system and the
emergency equipment with which the rig is provided, offers
the best opportunity for saving everyone’s life. This is
usually described in section five of the safety case. In the
UK it is usually the summary of the PFEER Assessment, but it
should describe the emergency equipment and systems to be
used on the rig. Remember that a major accident is one where
there are likely to be more than five fatalities, and that
occupational accidents have a place elsewhere. When it comes
to emergency equipment we live in a prescriptive world with
standards set by the flag state of the unit, usually for oil
rigs, in accordance with the MODU Code. It is common for the
qualitative risk assessment process to determine the
adequacy of the emergency arrangements, and of course
nothing prevents the owners of the unit from doing better
than would be required by the regulations. Once more the
section should summarise the emergency provisions, and the
safety case process gives the workforce the opportunity of
looking at them, and making improvements to the basic
requirements. The UK regulations require that all the
emergency arrangements be interlocked in a workable way,
including the station bill, the offshore emergency manual
and the onshore procedures and organisation. When discussing
the arrangements during the risk assessment it is up to the
facilitator to make sure that the emergencies are
realistically considered. It is a common approach to provide
emergency response documentation which does nothing more
than lay out a basis for a weekly exercise. We have to do
better.
And finally the safety case of old contained a section which
was called “Justification for Continued Operations”, which
was more or less the section containing the recommendations
from the risk assessments and the programme for their
implementation, or indeed why they were not to be
implemented. If one is to approach the safety case process
as a means of keeping the workforce safe while they are
offshore it is essential to detail such a programme. No
installation is perfect. No safety management system is
without fault. The safety case process provides a means of
using the collective knowledge and expertise of the
workforce to tease out these failings and improve systems
and procedures, and as participants they will then be likely
to know what it is, where it can be found and how best to
use it.
Victor Gibson. September 2012